Department Of Energy Approves Line Sending Canadian Hydroelectric Power To NYC

ALBANY, N.Y. (CBSNewYork/AP) -- Federal energy regulators this week gave final approval for construction of a 330-mile electric transmission line, which will carry lower-cost hydroelectric power from Canada to New York City.

In a decision dated Wednesday, the U.S. Department of Energy said the permit requires some final concerns to be addressed by Albany-based Transmission Developers Inc. but otherwise clears the way for the 1,000-megawatt Champlain Hudson Power Express transmission line. The project has been in development since 2008.

The agency said the decision was ``based on consideration of the potential environmental impacts, impacts on the reliability of the U.S. electric power supply system under normal and contingency conditions, and the favorable recommendations of the U.S. Departments of State and Defense.''

After the environmental impact statement was approved in August, the Department of Energy got some additional agency and public comment and decided the developer needs to work with the Coast Guard and others to avoid navigation hazards, including anchor snags. There also will be ongoing state and federal regulatory work to protect fish, wildlife and cultural resources including historic sites.

The project is aimed at saving about 2 percent to 3 percent on energy bills in New York City, where power is expensive and in high demand. The developer has said ratepayers also will see price breaks from Long Island to Albany.

The line is to run under the length of Lake Champlain, through parts of the Hudson, Harlem and East rivers and beneath railroad rights of way en route from Quebec to Con Edison in Queens.

Transmission Developers chief executive officer Donald Jessome said Friday that two Army Corps of Engineers permits are expected to be in hand in October and the company will move ahead with other aspects of the project, including financing, with the goal of starting construction next year.

Construction is expected to take about four years, create about 300 jobs and cost about $2 billion.

The developers of the Champlain Hudson Power Express also have proposed the New England Clean Power Link, a 150-mile, 1,000-megawatt transmission cable under Lake Champlain from Canada to Vermont. That project was announced last fall.

Some upstate New York legislators have opposed the Quebec-to-New York City power line, saying it would compete with New York power producers. Supporters say it would make the state less dependent on the 2,000-megawatt Indian Point nuclear power plant, which provides about one-fourth of the power used in New York City and Westchester County. Gov. Andrew Cuomo has said he wants to close the aging nuclear plant but needs an alternate source for the energy it produces.

You May Also Be Interested In These Stories:

(TM and © Copyright 2014 CBS Radio Inc. and its relevant subsidiaries. CBS RADIO and EYE Logo TM and Copyright 2014 CBS Broadcasting Inc. Used under license. All Rights Reserved. This material may not be published, broadcast, rewritten, or redistributed. The Associated Press contributed to this report.)

View CBS News In
CBS News App Open
Chrome Safari Continue
Be the first to know
Get browser notifications for breaking news, live events, and exclusive reporting.